A RACI matrix (also called a RACI chart or responsibility assignment matrix) is a table that shows who does what in a project or process. Tasks are listed in rows, people or roles in columns, and each cell holds one of four letters: Responsible, Accountable, Consulted or Informed. It removes the two most common sources of confusion in teamwork: tasks nobody owns and tasks that several people believe they own.
The four RACI roles
Responsible (R): the person or people who do the work.
Accountable (A): the one person who answers for the result and approves it. There is exactly one A for each task.
Consulted (C): people whose input is needed before or during the work. Communication goes both ways.
Informed (I): people who are told about progress or the outcome. Communication goes one way.
How to create a RACI matrix
List the tasks, deliverables or decisions down the left side. Keep them at a similar level of detail.
List the roles across the top. Roles such as "Designer" last longer than names.
Fill in each cell with R, A, C, I or leave it empty.
Check each row. Every task needs one A and at least one R.
Check each column. A person with too many R cells is overloaded, and a column with no letters may not need to be on the project.
Agree and share. Review the chart with everyone on it before the work starts.
RACI matrix rules
One Accountable for each task, never two.
Keep the number of Consulted people small, because each one slows a decision.
The same person can be both Responsible and Accountable for a small task.
Update the chart when roles or scope change.
RACI matrix example
For a website relaunch with four roles:
Task | Project lead | Designer | Developer | Marketing |
|---|---|---|---|---|
Page designs | A | R | C | C |
Build pages | A | C | R | I |
Launch announcement | I | C | I | A, R |
Common mistakes
Too many tasks. A chart with a hundred rows is not read. Stay at the level of deliverables.
Using it to settle conflicts after the fact. Agree on it at the start.
Confusing R and A. The person who does the work is not always the one who answers for it.
RACI and related tools
A RACI matrix covers the delivery team. A stakeholder map covers everyone with an interest in the project, and a swimlane diagram shows the same responsibilities as a flow over time. Teams that set goals with OKRs often add a RACI for each initiative.
RACI matrix in MockFlow
The RACI matrix skill drafts the chart from a short description of the project, as a table on the board that the team can edit together. Keep it beside the project plan and the stakeholder map so roles stay visible. See MockFlow for operations and the planning templates for more.