PI planning is the planning event of the Scaled Agile Framework (SAFe) in which all the teams that work on one product or solution plan their next increment of work together. PI stands for Program Increment, renamed Planning Interval in recent versions of SAFe: a period of typically 8 to 12 weeks made up of several sprints. The group of teams is called an Agile Release Train. The event usually lasts two days and aligns everyone on shared goals, dependencies and risks.
Who takes part
Agile teams: developers, testers, designers, product owners and scrum masters.
Business owners and product management: they present the vision and priorities and assign business value to objectives.
Release Train Engineer: the facilitator of the event.
System architects and other stakeholders who support the teams.
A typical PI planning agenda
Day one
Business context and product vision.
Architecture vision and planning guidance.
Team breakouts: each team drafts its plan for every sprint and identifies dependencies and risks.
Draft plan review and a management review of problems found.
Day two
Planning adjustments based on the review.
Team breakouts to finish plans and objectives.
Final plan review.
Risk review, confidence vote and a short retrospective on the event.
PI planning outputs
PI objectives: a short list of goals for each team, with business value assigned by the business owners.
Planning board: a board showing feature delivery dates, milestones and dependencies between teams, often drawn with strings or lines between cards.
Risks: each risk is discussed and marked Resolved, Owned, Accepted or Mitigated, known as ROAM.
Confidence vote: a fist of five vote on whether the plan is achievable.
Tips for remote and hybrid PI planning
Give each team its own area on a shared board, plus one shared area for the planning board.
Prepare the backlog and the capacity of each team before the event.
Use timeboxing for breakouts and keep a parking lot for questions.
Make dependencies visible as soon as they are found.
PI planning vs sprint planning
Sprint planning covers one team and one sprint. PI planning covers many teams and several sprints, and it focuses on objectives and dependencies more than on individual tasks. During the increment, each team still holds its daily standup and sprint retrospective. The plan often feeds a product roadmap.
Example
Five teams build a banking app. In the first breakout, the payments team finds that its new transfer screen depends on an API from the platform team planned for sprint three. The two teams link the cards on the planning board and the platform team moves the API to sprint two. In the confidence vote the train averages four, and the plan is accepted.
PI planning in MockFlow
A MockFlow board gives every team room for its sprints and a shared space for objectives, dependencies and risks, with calls held on the same board. Start from the agile team sprint planner template, use the sprint task planner skill to draft a team plan, and estimate with planning poker. More are in the sprint planning tools, and the whiteboard for meetings and whiteboard for product managers pages show how planning sessions run on a board.